[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941924,608,1,"单选题","按规定等级判断项目成功的程度，原定目标大部分实现，项目功能、效益和影响基本达到预期要求的等级是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","完全成功",false,{"key":16,"text":17,"correct":18},"B","基本成功",true,{"key":20,"text":21,"correct":14},"C","部分成功",{"key":23,"text":24,"correct":14},"D","不成功","考点:项目目标评价与可持续性评价。基本成功：原定目标大部分实现，项目功能、效益和影响基本达到预期要求。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]