[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941920,608,1,"单选题","政府投资项目实行审批制，一般不再审批（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","项目可行性研究报告",{"key":19,"text":20,"correct":14},"C","初步设计",{"key":22,"text":23,"correct":24},"D","开工报告",true,"考点:审批制项目决策程序。政府投资项目实行审批制，包括审批项目建议书、项目可行性研究报告、初步设计。除特殊情况影响重大的项目需要审批开工报告外，一般不再审批开工报告，同时应严格政府投资项目的初步设计、概算审批工作。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]