[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941916":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941916,608,2,"多选题","下列关于外商投资项目决策程序的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各类外商投资项目实行核准和备案两种方式分类管理",true,{"key":16,"text":17,"correct":18},"B","总投资（含增资）限额及以上的鼓励类项目，总投资（含增资）限额及以上的限制类（不含房地产）项目，由国务院核准",false,{"key":20,"text":21,"correct":14},"C","限额以下鼓励类项目，由地方政府核准",{"key":23,"text":24,"correct":14},"D","对于特别重大的项目，可以实行专家评议制度",{"key":26,"text":27,"correct":14},"E","对于不在《核准目录》和《外商投资准人负面清单》规定核准范围以外的外商投资项目，由地方敏府投资主管部门备案","ACDE","考点:投资项目决策程序。选项 B，总投资（含增资）限额及以上的鼓励类项目，总投资（含增资）限额及以上的限制类（不含房地产）项目，由国家发展改革委核准。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]