[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941914":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941914,608,2,"多选题","项目申请报告主要是从（ ）等方面对拟建项目进行论证。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资源利用",true,{"key":16,"text":17,"correct":18},"B","投资估算",false,{"key":20,"text":21,"correct":14},"C","规划布局",{"key":23,"text":24,"correct":14},"D","征地移民",{"key":26,"text":27,"correct":14},"E","生态环境","ACDE","考点:项目前期咨询成果的相互关系。项目申请报告主要是从规划布局、资源利用、征地移民、生态环境、经济和社会影响等方面对拟建项目进行论证，而市场、技术、资金来源、财务效益等不涉及政府公权力等“纯内部”问题，不作为主要内容，但需要简要说明项目有关内容，作为对项目核准提供项目背景、外部影响评估的基础材料。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]