[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941891,608,1,"单选题","企业投资项目与政府投资项目在决策程序上的一个重要区别在于是否需要编制（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","初步可行性研究报告",false,{"key":16,"text":17,"correct":14},"B","环境影响评价报告",{"key":19,"text":20,"correct":14},"C","可行性研究报告",{"key":22,"text":23,"correct":24},"D","项目申请报告",true,"考点:项目决策的含义和原则。企业编制的项目申请书，是政府投资主管部门办理核准或备案行政许可的依据，以政府核准或备案为决策标志。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]