[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941871,608,1,"单选题","初步可行性研究主要是采用近年同行业类似项目及其生产水平的类比方法，估算项目总投资，其允许误差（ ）左右。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","10%",{"key":19,"text":20,"correct":14},"C","15%",{"key":22,"text":23,"correct":24},"D","20%",true,"考点:项目前期咨询成果的相互关系。初步可行性研究主要是采用近年同行业类似项目及其生产水平的类比方法，估算项目总投资（允许误差 20%左右），经济效益评价可以静态为主，或与动态分析相结合。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]