[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941863":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941863,608,2,"多选题","下列关于初步可行性研究的说法，错误的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","初步可行性研究报告是项目决策的依据",true,{"key":16,"text":17,"correct":18},"B","政府投资项目，允许初步可行性研究报告代替项目建议书",false,{"key":20,"text":21,"correct":14},"C","初步可行性研究的主要目的是论证项目建设的必要性和可行性",{"key":23,"text":24,"correct":18},"D","初步可行性研究的深度介于投资机会研究和可行性研究之间",{"key":26,"text":27,"correct":18},"E","项目建议书与初步可行性研究报告之间的差别，主要是对研究成果具体阐述的详略","AC","考点:项目前期主要咨询成果的类型。选项 A 错误，可行性研究报告是项目决策的依据，选项 C 错误，初步可行性研究的主要目的是判断项目是否有必要性，是否值得投入更多的人力和资金进行可行性研究。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]