[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941861,608,1,"单选题","某建设项目以财务净现值为指标进行敏感性分析的有关数据如下表所示（单位万元），则按净现值确定的敏感程度由大到小的顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-②-③",false,{"key":16,"text":17,"correct":18},"B","②-①-③",true,{"key":20,"text":21,"correct":14},"C","②-③-①",{"key":23,"text":24,"correct":14},"D","③-②-①","考点:敏感性分析。对于相同的变化幅度，如果使得净现值的变化量的绝对值越大，则表示越敏感。以变动+10%为例：建设投资使得净现值的变动为：807.94-861.44=-53.5；营业收入使得净现值的变动为：1019.80-861.44=158.36；经营成本使得净现值的变动为：847.47-861.44=-13.97。敏感度从高到低依次为：营业收入、建设投资和经营成本。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]