[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941860":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941860,608,2,"多选题","关于概率树分析的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","通常假定输入变量之间是相关的",false,{"key":16,"text":17,"correct":14},"B","净现值小于零的概率越接近1，风险越小",{"key":19,"text":20,"correct":21},"C","净现值期望值为各加权净现值之和",true,{"key":23,"text":24,"correct":21},"D","该方法不适于输入变量存在相互关联的情况",{"key":26,"text":27,"correct":14},"E","评价指标通常按由大到小的顺序排列计算累计概率","CD","考点:风险估计。假定输入变量之间是相互独立的。净现值小于零的概率越接近1，风险越大。评价指标通常按由小到大的顺序排列计算累计概率。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]