[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941854":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941854,608,2,"多选题","经验表明，对建设项目应予以进行敏感性分析的因素包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","产出品价格",true,{"key":16,"text":17,"correct":14},"B","人民币汇率",{"key":19,"text":20,"correct":14},"C","建设期",{"key":22,"text":23,"correct":14},"D","可变成本",{"key":25,"text":26,"correct":27},"E","固定成本",false,"ABCD","考点:敏感性分析。经验表明，对建设项目应予进行敏感性分析的因素包括建设投资、产出价格、主要投入物价格或可变成本、运营负荷、建设期以及人民币汇率等，根据项目的具体情况也可选择其他因素",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]