[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941832,608,1,"单选题","某项目基本方案的内部收益率为15.3％，当建设投资上升10％时，内部收益率为12.6％，则建设投资的敏感度系数为 （ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.27",false,{"key":16,"text":17,"correct":18},"B","-1.76",true,{"key":20,"text":21,"correct":14},"C","1.26",{"key":23,"text":24,"correct":14},"D","-0.82","考点:敏感性分析。敏感度系数是项目效益指标变化的百分率与不确定因素变化的百分率之比。敏感度系数高，表示项目效益对该不确定因素敏感程度高，提示应重视该不确定因素对项目效益的影响。敏感度系数计算公式如下：E=（△A／A）／（△F／F）。式中：E—评价指标 A 对于不确定因素 F 的敏感度系数；△A／A-不确定因素 F 发生△F／F 变化时，评价指标 A 的相应变化率（％）；△ F／F-不确定因素 F 的变化率（％）。将题干中的数据代入公式得：△A／A=（0.126-0.153）／0.153=- 0.176，E=-0.176／0.1 =-1.76。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]