[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941829,608,1,"单选题","关于建设项目风险的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不同阶段的风险基本相同",false,{"key":16,"text":17,"correct":18},"B","风险具有客观存在性",true,{"key":20,"text":21,"correct":14},"C","投机风险只能带来损失",{"key":23,"text":24,"correct":14},"D","自然灾害属于特殊风险","考点:不确定性与风险的概念。A 选项，投资项目的不同阶段存在的主要风险有所不同。C 选项，投机风险可能带来损失，也可能产生利益。D 选项，自然灾害属于基本风险。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]