[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941810,608,2,"多选题","投资项目社会评价的目的在宏观层面上不包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制订一个能够切实完成项目目标的机制和组织模式",true,{"key":16,"text":17,"correct":18},"B","满足人们的基本社会需求",false,{"key":20,"text":21,"correct":18},"C","保证不同地区之间的公平协调发展",{"key":23,"text":24,"correct":14},"D","防止或尽量减少项目对地区社会环境造成的负面影响",{"key":26,"text":27,"correct":18},"E","充分利用地方资源.人力.技术和知识，增强地方的参与程度","AD","考点:社会评价的目的、作用和适用范围。选项 AD 属于在项目层面的社会评价目的。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]