[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941809":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941809,608,2,"多选题","项目的社会可持续性分析是对项目生命周期的总体发展的分析，包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","对财政收入的影响",false,{"key":16,"text":17,"correct":14},"B","对居民收入的影响",{"key":19,"text":20,"correct":14},"C","项目对所在地区文化遗产的影响",{"key":22,"text":23,"correct":24},"D","项目受益者对社会可持续性的影响分析",true,{"key":26,"text":27,"correct":24},"E","项目受损者对社会可持续性的影响分析","DE","考点:社会评价的主要内容。项目的社会可持续性分析是对项目生命周期的总体发展的分析。包括：（1）社会效果可持续性分析；（2）项目受益者对社会可持续性的影响分析；（3）项目受损者对社会可持续性的影响分析。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]