[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941787":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941787,608,2,"多选题","关于建设项目详细社会评价的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","详细社会评价是可行性研究阶段的工作内容",true,{"key":16,"text":17,"correct":14},"B","详细社会评价一般以初步社会评价为基础",{"key":19,"text":20,"correct":14},"C","详细社会评价考虑项目的工程技术方案",{"key":22,"text":23,"correct":24},"D","详细社会评价着眼于正面社会因素",false,{"key":26,"text":27,"correct":24},"E","详细社会评价以定量分析为主","ABC","考点:社会评价的目的、作用和适用范围。详细社会评价是在可行性研究阶段广泛应用的一种评价方法，是在初步社会评价的基础上，采用定量和定性分析相结合的方法，结合项目的工程技术方案，进一步研究与项目相关的社会因素和社会影响程度，进行详细论证并预测风险程度，系统地评价社会影响。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]