[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941783":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941783,608,2,"多选题","项目利益相关者的划分中包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目受益人",true,{"key":16,"text":17,"correct":14},"B","项目受害人",{"key":19,"text":20,"correct":14},"C","项目受影响人",{"key":22,"text":23,"correct":24},"D","项目负责人",false,{"key":26,"text":27,"correct":14},"E","其他利益相关者","ABCE","考点:利益相关者分析方法。项目利益相关者一般划分为：①项目受益人；②项目受害人；③项目受影响人；④其他利益相关者。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]