[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941749":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941749,608,2,"多选题","下列选项属于项目申请报告编制依据的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","《政府核准和备案投资项目管理条例》",true,{"key":16,"text":17,"correct":14},"B","项目申请报告编制的前置审批事项",{"key":19,"text":20,"correct":14},"C","项目可行性研究报告.专项报告以及相应的评估或审查意见",{"key":22,"text":23,"correct":24},"D","申报单位及项目概况",false,{"key":26,"text":27,"correct":14},"E","核准招标内容的企业投资项目，还应附有关招标内容","ABCE","考点:项目申请报告的编制依据和要求。项目申请报告编制依据包含：（1）有关法律、法规、政策文件，比如《政府核准和备案投资项目管理条例》；（2）项目申请报告编制的前置审批事项；（3）项目可行性研究报告、专项报吿以及相应的评估或审查意见；（4）核准招标内容的企业投资项目，还应附有关招标内容；（5）投标、购并、或合资合作项目的特殊要求。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]