[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941735":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941735,608,1,"单选题","一般企业投资项目编制项目申请报告的前置审批事项包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","用地预审",true,{"key":16,"text":17,"correct":18},"B","节能审查和用地预审",false,{"key":20,"text":21,"correct":18},"C","环境影响评价和规划选址",{"key":23,"text":24,"correct":18},"D","社会稳定风险评估","考点:项目申请报告的含义和作用及类别。项目申请报告编制的前置审批事项包括规划选址（仅指以划拨方式提供国有土地使用权的建设项目）和用地预审（用海预审）。对重特大项目，也应将环评（海洋环评）审批作为前置条件。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]