[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941676,608,1,"单选题","建设方案比选方法中，按各备选方案所含的因素（相同因素和不同因素）进行定量和定性的全面对比的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","整体的方案比选",true,{"key":16,"text":17,"correct":18},"B","专项的方案比选",false,{"key":20,"text":21,"correct":18},"C","定性的方案比选",{"key":23,"text":24,"correct":18},"D","定量的方案比选","考点:建设方案间的关系类型及建设方案比选方法的类型。整体的方案比选是按各备选方案所含的因素（相同因素和不同因素）进行定量和定性的全面对比。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]