[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941672":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941672,608,2,"多选题","下列评价指标中，可直接用于互斥型方案比选的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","净现值",true,{"key":16,"text":17,"correct":14},"B","净年值",{"key":19,"text":20,"correct":21},"C","投资回收期",false,{"key":23,"text":24,"correct":21},"D","内部收益率",{"key":26,"text":27,"correct":14},"E","年折算费用","ABE","考点:建设方案的经济比选。可直接用于互斥型方案比选的有净现值、净年值和年折算费用。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]