[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941655":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941655,608,2,"多选题","关于政府和社会资本合作（PPP）项目物有所值评价的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","物有所值评价必须进行定量评价",false,{"key":16,"text":17,"correct":18},"B","政府机构能力是物有所值评价内容之一",true,{"key":20,"text":21,"correct":18},"C","物有所值评价是判断项目是否采用PPP模式实施的决策基础",{"key":23,"text":24,"correct":18},"D","定量评价的前提是假定PPP模式和政府传统投资模式的产出绩效相同",{"key":26,"text":27,"correct":14},"E","物有所值验证只有一次机会，一旦不能通过，就不再采用PPP模式","BCD","考点:实施方案编制内容的项目概况。选项 A 错误，物有所值评价现阶段以定性评价为主，鼓励开展定量评价。选项 E，进行项目物有所值分析和财政承受能力分析论证，通过二者验证的，由项目实施机构报政府审核，未通过验证的，可在实施方案调整后重新验证。重新验证仍不能通过的，不再采用政府和社会资本合作模式。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]