[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941654,608,1,"单选题","下列项目属于使用者付费+可行性缺口补助的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收费公路",false,{"key":16,"text":17,"correct":14},"B","水处理项目",{"key":19,"text":20,"correct":21},"C","城市综合管廊",true,{"key":23,"text":24,"correct":14},"D","市政绿化项目","考点: PPP 项目实施方案的项目交易结构。选项 AB 属于使用者付费，选项 D 属于政府付费。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]