[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941651,608,1,"单选题","区分新建和存量项目，以项目是否通过（ ）为依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目决策",false,{"key":16,"text":17,"correct":14},"B","项目后评价",{"key":19,"text":20,"correct":21},"C","竣工验收",true,{"key":23,"text":24,"correct":14},"D","交工验收","考点:实施方案编制内容的项目概况。区分新建和存量项目，以项目是否通过竣工验收为界限。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]