[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941649":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941649,608,2,"多选题","以下属于政府和社会资本合作（PPP）项目实施方案编制内容的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","技术方案",false,{"key":16,"text":17,"correct":18},"B","项目交易结构",true,{"key":20,"text":21,"correct":18},"C","物有所值论证",{"key":23,"text":24,"correct":14},"D","总体建设方案",{"key":26,"text":27,"correct":18},"E","风险识别与分配","BCE","考点:政府和社会资本合作（PPP）项目实施方案编制内容。实施方案的编制一般包括项目概况、风险识别与分配、项目运作方式、项目交易结构、合同体系、监管架构、社会资本采购、物有所值与财政承受能力论证等八个方面的内容，在具体编制时可结合项目特点和具体情况酌情增减。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]