[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941647":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941647,608,2,"多选题","政府和社会资本合作（PPP）项目实施方案中需进行风险识别与分配。以下风险因素中，一般情况下社会资本方需承担的风险有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","社会风险",false,{"key":16,"text":17,"correct":18},"B","融资风险",true,{"key":20,"text":21,"correct":14},"C","法律风险",{"key":23,"text":24,"correct":14},"D","不可抗力",{"key":26,"text":27,"correct":18},"E","维护风险","BE","考点:风险分配的结果。风险分配的结果： （1）政府方需承担的风险。政治和公共政策风险；社会和法律风险。 （2）社会资本方需承担的风险。如设计、融资和施工、运营、维护等。 （3）双方共同承担的风险。不可抗力因素等。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]