[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941645":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941645,608,2,"多选题","政府和社会资本合作（PPP）项目实施方案中需进行风险识别与分配。风险分配原则包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承担的风险程度与所得回报相匹配的原则",true,{"key":16,"text":17,"correct":18},"B","承担风险的一方具有承担风险意愿的原则",false,{"key":20,"text":21,"correct":14},"C","承担风险的一方能够将风险合理转移的原则",{"key":23,"text":24,"correct":14},"D","由对风险最有控制力的一方承担相应风险的原则",{"key":26,"text":27,"correct":18},"E","社会资本方不愿意承担的风险由政府方承担的原则","ACD","考点:风险分配原则。风险分配原则包括： 1.由风险控制力最强的一方承担相应风险的原则 2.风险的承担方能够将风险合理转移的原则 3.风险的承担程度与所得回报相匹配的原则",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]