[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941635":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941635,608,2,"多选题","项目方案变更管理视内容、投资大小可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","一般性变更",true,{"key":16,"text":17,"correct":18},"B","较大变更",false,{"key":20,"text":21,"correct":14},"C","重大变更",{"key":23,"text":24,"correct":18},"D","特别重大变更",{"key":26,"text":27,"correct":18},"E","设计变更","AC","考点: PPP 项目实施方案的合同体系。变更视内容、投资大小可分为一般性变更和重大变更，相关的标准可以参照现行各行业管理规定执行。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]