[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941629":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941629,608,1,"单选题","PPP 项目实施方案风险识别与分配中，属于系统性风险的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工风险",false,{"key":16,"text":17,"correct":14},"B","设计风险",{"key":19,"text":20,"correct":21},"C","经济风险",true,{"key":23,"text":24,"correct":14},"D","管理风险","考点:风险识别与分配。系统性风险包括：不可抗力风险，政策风险，经济风险。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]