[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941624,608,1,"单选题","政府和社会资本合作（PPP）项目实施过程中，监管体系一般不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理监管",true,{"key":16,"text":17,"correct":18},"B","履约监管",false,{"key":20,"text":21,"correct":18},"C","行政监管",{"key":23,"text":24,"correct":18},"D","公众监管","考点:监管架构和社会资本采购。政府和社会资本合作（PPP）项目实施过程中，监管体系一般包括履约监管、行政监管、公众监管等三个方面。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]