[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941623":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941623,608,2,"多选题","政府和社会资本合作（PPP）项目物有所值评价中，风险承担支出应充分考虑各类风险出现的概率和带来的支出责任，可采用（ ）进行测算。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","比例法",true,{"key":16,"text":17,"correct":14},"B","概率法",{"key":19,"text":20,"correct":14},"C","情景分析法",{"key":22,"text":23,"correct":24},"D","风险评价矩阵法",false,{"key":26,"text":27,"correct":24},"E","蒙特卡罗模拟法","ABC","考点:物业所值评价。风险承担支出应充分考虑各类风险出现的概率和带来的支出责任，可采用比例法、情景分析法及概率法进行测算。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]