[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941621":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941621,608,2,"多选题","政府和社会资本合作（PPP）项目实施方案编制的基本要求包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","约束性",false,{"key":16,"text":17,"correct":18},"B","科学性",true,{"key":20,"text":21,"correct":18},"C","专业性",{"key":23,"text":24,"correct":14},"D","时效性",{"key":26,"text":27,"correct":18},"E","有效性","BCE","考点:实施方案编制的基本要求。实施方案编制的基本要求：实施方案要具有科学性；实施方案要具有专业性；实施方案要具有有效性。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]