[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941612":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941612,608,2,"多选题","常用的回报机制及适用条件主要包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","使用者付费",true,{"key":16,"text":17,"correct":14},"B","政府付费",{"key":19,"text":20,"correct":21},"C","可行性缺口补助",false,{"key":23,"text":24,"correct":14},"D","使用者付费+可行性缺口补助",{"key":26,"text":27,"correct":21},"E","使用者付费+政府付费","ABD","考点: PPP 项目实施方案的项目交易结构。常用的回报机制及适用条件主要包括使用者付费，政府付费，使用者付费+可行性缺口补助。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]