[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941611":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941611,608,2,"多选题","PPP 项目政府和社会资本投资人合同体系中调整衔接边界包含（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","临时征用与接管",true,{"key":16,"text":17,"correct":18},"B","项目保险方案",false,{"key":20,"text":21,"correct":14},"C","合同变更和延期",{"key":23,"text":24,"correct":18},"D","项目合作期限",{"key":26,"text":27,"correct":18},"E","项目用地","AC","考点: PPP 项目实施方案的合同体系。调整衔接边界包括应急处理，临时征用与接管，合同变更和延期，合同解除，项目公司股权变更。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]