[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941571":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941571,608,2,"多选题","尽管投资估算在具体数额上允许存在一定的误差，但是必须达到以下要求（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","估算的范围应与项目建设方案所涉及的范围.所确定的各项工程内容相一致",true,{"key":16,"text":17,"correct":18},"B","估算的工程内容和费用构成齐全，计算合理，可适当提高估算标准",false,{"key":20,"text":21,"correct":14},"C","估算应做到方法科学.基础资料完整.依据充分",{"key":23,"text":24,"correct":14},"D","估算的准确度应能满足项目决策的要求",{"key":26,"text":27,"correct":18},"E","估算选用的指标与具体工程之间存在微小条件差异时，可不进行必要的换算","ACD","考点:投资估算。选项 B，估算的工程内容和费用构成齐全，计算合理，不提高或者降低估算标准。选项 E，估算选用的指标与具体工程之间存在标准或者条件差异时，应进行必要的换算或者调整。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]