[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941569":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941569,608,2,"多选题","生产规模和各装置的能力以（ ）计。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","小时",true,{"key":16,"text":17,"correct":14},"B","日",{"key":19,"text":20,"correct":21},"C","周",false,{"key":23,"text":24,"correct":21},"D","月",{"key":26,"text":27,"correct":14},"E","年","ABE","考点:建设方案概述和建设规模与产品方案。生产规模和各装置的能力以小时（或日）和年计。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]