[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941557,608,1,"单选题","下列投资项目的风险属于市场风险的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对项目的社会影响估计不足",false,{"key":16,"text":17,"correct":18},"B","消费者的消费习惯.消费偏好发生变化",true,{"key":20,"text":21,"correct":14},"C","对技术的适用性和可靠性认识不足",{"key":23,"text":24,"correct":14},"D","主要管理者能力不足","考点:风险分析和研究结论。选项 A 是环境与社会风险，选项 C 是技术与工程风险，选项 D 是组织管理风险。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]