[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941544":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941544,608,2,"多选题","总图运输中竖向布置的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工厂防洪标准及措施",true,{"key":16,"text":17,"correct":18},"B","厂区用地面积",false,{"key":20,"text":21,"correct":18},"C","容积率",{"key":23,"text":24,"correct":14},"D","场地排水方式",{"key":26,"text":27,"correct":14},"E","土石方工程量","ADE","考点:总图运输。当新建厂区占地面积较大，或自然地形坡度较大，或施工、生产、运输等方面有特殊要求时，应做竖向方案比较。提出推荐的竖向布置方案及设防说明。提出工厂防洪标准及措施场、地排水方式、土石方工程量等。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]