[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941531":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941531,608,1,"单选题","项目可行性研究经济分析中，水利枢纽项目的直接效益不能体现在（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","防洪效益",false,{"key":16,"text":17,"correct":14},"B","减於效益",{"key":19,"text":20,"correct":14},"C","发电效益",{"key":22,"text":23,"correct":24},"D","时间效益",true,"考点:经济分析。水利枢纽项目的直接效益体现为防洪效益、减淤效益和发电效益等，可按照行业和项目具体情况分别估算。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]