[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941526":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941526,608,1,"单选题","地质灾害危险性评估必须在（ ）之前进行。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","初步可行性研究阶段",false,{"key":16,"text":17,"correct":14},"B","厂址选择阶段",{"key":19,"text":20,"correct":21},"C","申请建设用地",true,{"key":23,"text":24,"correct":14},"D","可行性研究阶段","考点:建设方案。根据《地质灾害防治管理办法》和《地质灾害防治条例》要求，有可能导致地质灾害（主名包括崩塌、滑坡、泥石流、地面塌陷、地裂缝、地面沉降等）发生的工程项目建设和在地质灾害易发区内进行工程建设，在申请建设用地之前必须进行地质灾害危险性评估。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]