[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941524":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},941524,608,1,"单选题","若引进国外技术和进口设备，则需要在分析（ ）的前提下，进行技术经济分析比较，提出引进方式、引进和进口的范围、内容及理由。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","市场容量",false,{"key":16,"text":17,"correct":18},"B","国内技术",true,{"key":20,"text":21,"correct":14},"C","建设规模",{"key":23,"text":24,"correct":14},"D","投资成本","考点:建设方案研究与比选。若引进国外技术和进口设备，则需要在分析国内技术的前提下，进行技术经济分析比较，提出引进方式、引进和进口的范围、内容及理由。提出对可能引进技术的初步意见和建议。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]