[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941474,608,1,"单选题","社会稳定风险分析与评估，属于项目可行性研究中（ ）的内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险分析",false,{"key":16,"text":17,"correct":14},"B","社会影响分析",{"key":19,"text":20,"correct":14},"C","经济影响分析",{"key":22,"text":23,"correct":24},"D","土地利用及移民搬迁安置方案分析",true,"考点:可行性研究的内容。对于新增建设用地的项目，应分析项目用地情况，提出节约用地措施。涉及搬迁和移民的项目，还应分析搬迁方案和移民安置方案的合理性。该部分内容还涉及社会稳定风险分析与评估。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]