[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941472,608,1,"单选题","项目评价中，除建设投资和建设期利息外，项目总投资的构成内容还包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流动资金",true,{"key":16,"text":17,"correct":18},"B","预备费用",false,{"key":20,"text":21,"correct":18},"C","安装工程费",{"key":23,"text":24,"correct":18},"D","工程建设监理费","考点:投资估算与资金筹措。项目总投资，包括建设投资、建设期利息和流动资金。选项 BCD 属于建设投资内容。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]