[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941425":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},941425,608,1,"单选题","九力模型综合评价时，为体现评价结果的客观性，一般邀请熟悉企业的（ ）名左右的专家进行评价打分。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":14},"C","9",{"key":22,"text":23,"correct":24},"D","10",true,"考点:企业发展规划的分析方法。九力模型综合评价的方法可以采用专家评分法。为体现评价结果的客观性，一般邀请熟悉企业的 10 名左右的专家进行评价打分。打分标准借鉴利克特 5级量表，按照有利和不利两类。以研发能力为例，分为相当强（行业领先，5 分）、中上水平（4 分）、中等水平（3 分）、中下水平（2 分）、没有研发能力（1 分）。",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]