[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941390":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941390,608,2,"多选题","根据国家发展改革委《中央政府投资项目后评价报告编制大纲》，开展后评价工作应重点收集的资料有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目结算",false,{"key":16,"text":17,"correct":14},"B","项目施工图预算",{"key":19,"text":20,"correct":21},"C","项目竣工决算",true,{"key":23,"text":24,"correct":21},"D","经批准的投资估算",{"key":26,"text":27,"correct":21},"E","经批准的初步设计概算","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]