[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941284":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941284,608,2,"多选题","政府投资项目与企业投资项目决策的区别包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投资主体和资金来源不同",true,{"key":16,"text":17,"correct":18},"B","决策主体和依据不同",false,{"key":20,"text":21,"correct":14},"C","决策和管理模式不同",{"key":23,"text":24,"correct":14},"D","决策过程不同",{"key":26,"text":27,"correct":14},"E","投资范围和内容不同","ACDE","㈢政府投资项目与企业投资项目决策的区别 ⒈投资主体和资金来源不同 ⒉决策过程不同 ⒊投资范围和内容不同 ⒋决策和管理模式不同",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]