[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941227":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941227,608,2,"多选题","下列风险应对策略中，属于风险转移对策的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业务对外发包",true,{"key":16,"text":17,"correct":14},"B","向保险公司投保",{"key":19,"text":20,"correct":21},"C","建立应急储备资金",false,{"key":23,"text":24,"correct":21},"D","降低技术方案复杂性",{"key":26,"text":27,"correct":14},"E","合同中增加保证性条款","ABE","第二种风险转移方式又可细分为保险转移方式和非保险转移方式两种。保险转移方式是在工程项目实施阶段常见的风险对策之一。 非保险转移主要有三种方式：出售、发包、免责合同。",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]