[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941224":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},941224,608,2,"多选题","关于项目决策分析与评价中项目风险对策的说法，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制定风险对策需要权衡代价与损失",true,{"key":16,"text":17,"correct":18},"B","风险防范工作应在项目开工建设时进行",false,{"key":20,"text":21,"correct":18},"C","风险接受是项目业主主动选择的结果",{"key":23,"text":24,"correct":14},"D","业主与施工方签订总价合同来应对风险的做法属于风险转移",{"key":26,"text":27,"correct":14},"E","通过可行性研究彻底改变原方案来应对风险的做法属于风险回避","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"项目决策分析与评价","建筑工程",0]