[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941222,608,1,"单选题","关于风险分析的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险函数的两个基本变量是风险事件发生的概率和风险事件对项目目标的影响",true,{"key":16,"text":17,"correct":18},"B","风险分析的四个基本阶段是风险识别、风险定性分析、风险定量分析和确定风险等级",false,{"key":20,"text":21,"correct":18},"C","风险事件发生的概率与风险事件对项目的影响程度成正比",{"key":23,"text":24,"correct":18},"D","损失较小的风险事件均可定性为较小风险","一、投资项目风险分析流程 包括风险识别、风险估计、风险评价与对策研究四个基本阶段。 风险事件发生的概率与风险事件对项目的影响程度之间无必然联系。 ⒌风险等级",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]