[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941207":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},941207,608,1,"单选题","关于项目风险分析中概率树分析的说法，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该方法适用于风险因素相互独立的情况",true,{"key":16,"text":17,"correct":18},"B","该方法适用于测算风险事件发生的概率",false,{"key":20,"text":21,"correct":18},"C","该方法适用于风险因素随机选取的情况",{"key":23,"text":24,"correct":18},"D","该方法要求风险因素与效益指标符合线性关系","",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]