[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-941206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},941206,608,1,"单选题","下表给出了某项目的四种风险状态。根据该表，下列关于该项目概率分析的结论，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","净现值的期望值为430万元，净现值≥0的累计概率为50%",false,{"key":16,"text":17,"correct":14},"B","净现值的期望值为490万元，净现值≥0的累计概率为50%",{"key":19,"text":20,"correct":21},"C","净现值的期望值为430万元，净现值≥0的累计概率为70%",true,{"key":23,"text":24,"correct":14},"D","净现值的期望值为490万元，净现值≥0的累计概率为70%","P[NPV\u003C0]=0.3，净现值≥0 的累计概率为1-30%=70%",{"id":6,"name":27,"category":28,"favorite":29},"项目决策分析与评价","建筑工程",0]